ERC represented FRICO through the design approval process and construction of a major pipeline crossing of the Burlington/O’Brian Canal. To minimize canal shutdown time, a temporary bypass canal sized to convey 150-cfs was constructed. The project was allowed a 48-hour canal shut down window to connect and disconnect the temporary bypass. A 66-inch steel casing pipe containing a 48-inch sewer pipe was constructed across the Burlington/O’Brian Canal while the canal continued to operate through the temporary bypass. The project site is located near a major creek and significant dewatering was required during the project. The project was completed successfully and on-time within the agreed upon schedule and minimized impact to FRICO ‘s water conveyance.
PROJECT
Metro 2nd Creek Interceptor
Temporary Bypass

Pipeline Crossing

Temporary Bypass Confluence

Temporary Bypass Removal and Canal Restoration